Jupiter/Carlin Beach Project

Jupiter Inlet south to the southern boundary of Carlin Park

Picture of beach construction project 

    

Full Nourishment Project COMPLETED DECEMBER 26, 2021
  • Beach fill operations began December 7 and were completed December 26 2021. 
  • Equipment demobilization was complete 1/14/2022.
  • ​Approximately 409,000 cubic yards of sand was pumped onshore to restore the beach.​

Fact Sheet October 2021​​

History

Dredging Project COMPLETED APRIL 2021

​The U.S. Army Corps of Engineers in partnership the Jupiter Inlet District and with the Florida Inland Navigation District performed maintenance dredging of the Intracoastal Waterway and Jupiter Inlet where approximately 210,000 cubic yards of sand was placed in the northern Jupiter/Carlin project area.

Nourishment Project COMPLETED JANUARY 2020

ERM's Beaches Program managed a nourishment project to replace areas of the beachfront lost during Hurricane Irma.  Approximately 500,000 cubic yards of sand was pumped onshore and formed into a 1.05 mile long restored beach spanning from south of Jupiter Inlet to the southern boundary of Carlin Park.